Suffolk PCT

During the two sites’ modernisation works programmes, Wiremek were approached to assist in the design, manufacture and installation of new LV switchgear, auto/changeover panels and bespoke panel modifications and additions to existing switchgear across the two sites.

Access and space constraints directly affected the design of the new or replacement panels so as to minimise the need for any new site cabling therefore greatly reducing project costs and downtime of critical areas and operating theatres.

All these panel modifications and panel replacements were carried out over night shutdowns and were operational once more before they were required again the following morning.  This involved strategic project management on Wiremek’s behalf so as to tie in panel manufacture and delivery with the hospital so that we could deliver the project within time and butdget.